- The $59.1 million 2021-22 S-G school budget was approved today by a vote of 741 to 203, a margin of 78.5% to 21.5%.
- The $493,000 bus purchase proposal was approved by a vote of 740-204, a margin of 78.4 to 21.6%
- The $12.8 million capital project was approved by a vote of 739 to 207, a 78.2% to 21.8% margin.
Board member David Massaro was re-elected with 783 votes and board member Hal Talbot was re-elected with 772 votes.
The community will consider a $12.8 million capital project during community voting on Tuesday, May 18. Voting will be held from 7 .m. to 9 p.m. in the B-wing gymnasium at the high school.
There will be no impact on the tax levy because of this project. The district retires debt every year and this would replace that retiring debt.
This capital project includes new furnaces and roofs, replacing lead water lines and public address systems and a host of other upgrades at all six school buildings as well as other locations.
- Presentation from April 21 capital project meeting
- Public Information meetings scheduled for April 21 and May 5
- Here’s an overview brochure of the project
- Project proposed at October Board of Education meet
Major Scope of Work for the May 18 capital project:
Glen-Worden Elementary – $3,542,510
• Roof Replacement
• Heating System conversion from Steam to Hot Water/Boiler Replacement
• Canopy improvements
• Sidewalk, ramps, railing replacements
• Masonry repairs
• PA System replacement
High School – $3,002,950
• Replace galvanized domestic water piping and recirculation pumps
• Replacement of aging mechanical units
• PA System replacement
• Area ‘C’ sidewalk replacement/stormwater catch basin repair
Glendaal Elementary – $2,542,669
• Roof replacement
• Exterior door replacements
• Parking lot reconstruction, sidewalk repair, ramp railing repair
• Masonry repairs
• PA System replacement
Sacandaga Elementary – $1,728,452
• Sidewalk, steps, ramps, railing replacement
• Replacement of aging mechanical units and upgrade controls
• PA System replacement
Middle School – $1,580,817
• Parking reconstruction, sidewalk replacement, bus drive improvements
• Small gym rooftop mechanical unit replacement
• PA System replacement
Lincoln Elementary – $253,962
• Sidewalk repair
• PA System replacement
Field House – $76,382
• Abatement of pipes in ceiling
• Exterior door replacement
District Office – $39,051
• Sidewalk install
Maintenance Building – $33,207
• Chimney repair